In the “Employees”, “Heavy Equipment”, or “Materials” tabs, click on the “Rate” subtab.
Add rates to your resources and interim resources
Employees
Click on “New Rate” at the top right of the page
Select the organization, profession, and employee for whom you want to add a rate. You can add a rate to all employees in an organization, or to all trades or to a specific employee, or a combination of all three. See the table below to see the different combinations and the implications of these
Click on “Create”
Click on the “+” to the right of the line of the combinations you created
Add the effective date for when you want the hourly rate to start applying
Add another line to add another effective date to the same combination
Equipments
Click on “Equipment” at the top of the page then go to the “Rate” sub-tab.
Click on “+ New Rate” at the top right of the page
Select the organization, the type of equipment, the equipment as well as the unit. You can add a rate to all equipment in an organization, or to all types of equipment or to specific equipment, or a combination of all three. See the table below to see the different combinations and the implications of these
Click on “Create”
Click on the “+” to the right of the line of the combinations you created
Add the effective date for when you want the hourly rate to start applying
Add regular hourly rate
Add another line to add another effective date to the same combination
Materials
Click on “Materials” at the top of the page then go to the “Rates” sub-tab.
Click on “+ New Rate” at the top right of the page
Select the organization or equipment for which you want to add a rate. You can add a rate to all materials in an organization or to specific hardware, or a combination of both. See the table below to see the different combinations and the implications of these
Click on “Create”
Click on the “+” to the right of the line of the combinations you created
Add the effective date for when you want the unit rate to start applying
Add unit rate
Add another line to add another effective date to the same combination
Project control
You can also enter project-level rate presets. These presets will then take priority over the global presets. They work exactly the same way.
To visualize this feature, follow these steps:
Click on the tab Project.
Click on the view “Control” (3rd icon).
Select the project in question.
Click on the tab “Rate”.
You will then see three sub-tabs: Employees, Equipment and Materials. Their use is the same as the global rates (see documentation above).
Importing a file
To make it easier to add your rates in Civalgo, we also added the possibility of adding rates using an easy import!
To do this, all you need to do is:
Click on the employee tab at the top of the page
Click on the “Import” button at the top right of the page